Why an automatic line is hard to schedule
An automatic green sand moulding line produces dozens or hundreds of moulds an hour. It is the most expensive resource in the foundry and almost always the bottleneck: every minute lost is never recovered. Yet the sequence of items depends on many constraints that affect one another.
The challenges, one by one
Pattern plate changes
Every change of pattern or plate takes line time. Long runs reduce changes, but customer orders arrive smaller and more frequent. The trade-off between the number of changes and meeting due dates is the first decision in scheduling.
Full plates and half plates
The line runs either a full plate, which takes 100%, or two half plates at 50% each. A pattern on a half plate cannot run on its own: it must always be paired with another 50% pattern, and the two must be in the same alloy, because they end up in the same flask and the same heat.
The problem arises when quantities do not match. If 50 flasks of pattern A are needed, other 50% patterns must run next to A for a total of 50 flasks: for example B for 30 flasks and then, after a half plate change, C for the remaining 20. For every pairing the schedule must check:
- same alloy for the paired patterns;
- quantities: when one half finishes first, another compatible pattern is needed to complete the other;
- half plate changes: each one is a set-up, to be minimised and placed at the right moment;
- similar cooling times, otherwise the slower pattern sets the pace for both;
- due dates, so as not to produce a pattern too early just to “fill” the free half.
When no compatible pattern is available, the alternative is to over-produce one of the two, tying up stock and cash. Choosing the best pairings week after week across dozens of patterns is a combinatorial problem that can only be partly solved by hand.
Continuous moulding and pouring
On an automatic line pouring follows moulding without interruption. Melting and holding furnaces must have the right alloy, in the right quantity, at the right temperature. An alloy change should be placed where the line already has a pause or a plate change, not in the middle of a run.
Cooling on the line
The cooling line has a fixed length. Heavy castings that need more time in the mould before shakeout force a lower cycle rate. Scheduling them together, or in dedicated slots, avoids slowing down all the other items.
Cores and core setting
Items with many cores take longer to set, and core setting can become the real limit on the cycle rate. The core shop has to produce cores before the line needs them, but not too far ahead: cores age and take up space.
Green sand
The sand preparation plant has a capacity, and at high cycle rates the sand temperature rises. Very demanding sequences of heavy castings can put the sand under strain even before the line.
Customers and deliveries
Automatic lines often work for high-volume production, for example automotive, with delivery schedules updated continuously. The plan has to be recalculated often, without losing sight of plate changes and pairings already decided.
How it is usually planned
The planner builds the sequence in a spreadsheet or on a whiteboard, drawing on years of experience with the line. Pairings of half-plate patterns are decided “from memory”, alloy changes are agreed verbally with the melt shop, and the core shop follows its own programme. It works until a rush order arrives or a furnace goes down: at that point the plan is redone by hand.
The limits of spreadsheets and generic ERP systems
- No pattern plate data: the ERP does not know which patterns take a full or a half plate, or which can be paired.
- Capacity in pieces, not in flasks: the real load on the line cannot be seen.
- Plate changes and alloy changes invisible: the cost of a wrong sequence only shows up at the end of the shift.
- Core shop disconnected: core shortages are discovered at core setting.
- No scenarios: you cannot compare in advance the plan with and without a pairing or an extra shift.
How FOND/WISE handles it
FOND/WISE holds the data needed to schedule the line: for each pattern the number of impressions, the pattern plate type and size, the plate occupation on the line (full plate at 100% or half plate at 50%), the gross weight, the alloy and the pouring temperatures, together with the daily capacity of the line in flasks, gross kg and times. In the daily programme the plan can be filtered and grouped by alloy and plate type, and progress comes in from the shop floor through the MES.
FIP’s AI production scheduling uses this data to calculate the sequence: the line’s rules are written in plain language, for example “the line makes at most 80 flasks an hour”, “no more than 4 plate changes per shift” or “a pattern on a half plate must always be paired with another 50% pattern in the same alloy”. In a few minutes the planner has a feasible plan over several weeks, with plate changes, delays and bottlenecks already highlighted, and can compare alternative scenarios.
Key features
Plate and pattern data
Impressions per pattern, plate type and size, occupation on the line, gross weight and alloy.
Line capacity
Flasks per day, gross kg and times as limits for the plan.
Grouping by alloy and plate
Daily programme filtered and sorted to reduce changeovers.
Rules in plain language
Plate changes, half plates and cooling described in natural language.
Scenarios side by side
An extra shift, a furnace down, a rush order: alternative plans compared.
Progress from the shop floor
Moulds made and pours declared in the MES, plan always up to date.
Worked example
An automatic flask line has to produce four ductile iron items in EN-GJS-400-15 in one shift. Three are on a half plate (50%), one on a full plate (100%). Illustrative values.
| Pattern | Plate occupation | Flasks required |
|---|---|---|
| A | 50% | 50 |
| B | 50% | 30 |
| C | 50% | 20 |
| D | 100% | 120 |
Pattern A cannot run on its own: the other half of the line must be taken by another 50% pattern in the same alloy. The quantities do not match, so the sequence becomes:
| Block | First half | Second half | Flasks |
|---|---|---|---|
| 1 | A | B | 30 |
| 2 | A | C (change B → C) | 20 |
| 3 | D, full plate | 120 |
A runs for 50 flasks without interruption, while next to it the half plate is changed from B to C after 30 flasks. All three patterns finish exactly at the quantities required.
If C were in a different alloy it could not run next to A. Another 50% pattern in the same alloy would be needed for the last 20 flasks, or B would have to be over-produced, tying up stock and cash. Multiplied by dozens of patterns a week, choosing which patterns to pair, in what order and with how many changes is a problem that can only be partly solved by hand.
Frequently asked questions
What is half plate pairing?
The line runs either a full plate, which takes 100%, or two half plates at 50% each. A pattern on a half plate must always be paired with another 50% pattern in the same alloy, because both halves end up in the same flask and the same heat. If the two quantities do not match, the half plate next to it is changed mid-run for another compatible pattern.
Why are pattern plate changes so critical?
Because at every change the line stops or slows down, and on a high-rate line even a few minutes are worth dozens of moulds. With ever smaller batches, changes increase: scheduling has to group them intelligently without delaying deliveries.
How does cooling affect scheduling?
The cooling line has a fixed length: heavy castings, which have to stay in the mould longer before shakeout, force a lower cycle rate. Scheduling items with similar cooling times together avoids slowing down the whole line.
What happens if the cores are not ready?
The line stops, or the item has to be changed at the last minute. That is why the core shop programme must be derived from the line sequence, with the right lead time but without letting cores age.
Does pouring have to follow the moulding rate?
Yes. On an automatic line moulding and pouring run continuously: melting and holding furnaces must always have the right alloy in sufficient quantity. An unplanned alloy change slows or stops the line.