Hand moulding and large castings scheduling: floor space, flasks, heats and cooling

With large castings a single mould can occupy an area of the shop for weeks, need a whole furnace and be worth as much as a month of series production. Scheduling hand moulding means managing floor space, flasks, teams, cranes and heats as scarce resources, over long lead times and with very little margin for error.

RC Informatica technical team · Published November 21, 2026

Why large castings are scheduled differently

In hand moulding with no-bake sand, in large flasks or in the pit, you do not think in moulds per hour but in days per mould. Each casting is often an order in its own right, with a dedicated pattern, long lead times and a high value. Scheduling has to manage resources that stay occupied for a long time and that affect one another.

The challenges, one by one

Floor space

Every mould occupies an area of the shop from moulding to shakeout. Space is a resource to be scheduled like a machine: if there is none, a finished mould cannot be placed, or a pour cannot be made.

Large flasks

Large flasks are few and stay occupied until shakeout, sometimes for weeks. An order that slips blocks the flask for the next one.

Long moulding times

Moulding, resin curing, coating, drying, core setting and closing take from many hours to several days per mould. The steps have to be coordinated with the available teams and with the shifts.

Moulding teams and cranes

Capacity depends on people: teams of skilled moulders, overhead cranes and other cranes. Two large moulds to be turned over or closed at the same time may need the same crane.

Castings that take a full furnace

A single casting can need the full charge of a furnace, with suitable ladles and handling equipment. The poured weight is limited by the capacity of the furnace and the ladle, and on that day the furnace pours nothing else. The pouring day is an event to be prepared, with alloy, temperature and minimum charge all respected.

In-mould cooling

Cooling of large castings lasts days or weeks. The plan has to consider when the flask and the floor space become free again, not just when the pour takes place.

Patterns and one-off orders

The pattern often belongs to the customer or comes from the patternmaker. Until it is available, moulding cannot start. Many orders are one-off pieces or small series, each with its own routing.

Long downstream steps

After pouring come knockout, cutting, heat treatment, any repair welding, non-destructive testing and machining, often as outside processing. The delivery date depends on the whole chain.

Value and risk of a single casting

A scrap costs a great deal and is found late. The plan must be able to be recalculated immediately, with the consequences for all the other orders.

How it is usually planned

The production manager keeps the plan on a whiteboard or in a spreadsheet, often with a hand-drawn layout of the shop. Pouring dates are decided in meetings with the melt shop, flask availability is known to the people on the floor, and pattern delays are discovered when the team is already ready to start.

The limits of spreadsheets and generic ERP systems

  • Space and flasks not managed as resources: the ERP only sees orders and operations.
  • Cooling times ignored: the real availability of flasks cannot be seen.
  • Castings that saturate a furnace not represented: the plan does not know that the furnace is taken by a single heat that day.
  • Patterns not linked: a pattern that is late or under maintenance does not block the plan.
  • No scenarios to assess the effect of a delay or a scrap on the other orders.
Fond/Wise

How FOND/WISE handles it

FOND/WISE manages the order and casting data: patterns with status, location and maintenance (including when they are at the patternmaker or owned by the customer), core boxes, gross weight, alloy, pouring temperatures, routings with internal and outside operations and their lead times, heat treatment and outside processing. Progress on every step comes in from the shop floor through the MES, and an alert flags at once a pattern that is under maintenance or unavailable.

FIP’s AI production scheduling plans moulding and pouring with the shop’s rules written in plain language, for example “the large flask stays occupied for up to 10 days after pouring”, “furnace 1 does not pour below 900 kg” or “the pump body needs the full charge of furnace 2”. The plan covers several weeks, shows flask and furnace load day by day and explains why an order is late.

Discover AI scheduling on FIP →

Key features

Patterns and core boxes

Status, location, maintenance and unavailability alerts.

Flasks as a resource

Flasks occupied until shakeout, included in the plan’s constraints.

Heavy pours

Minimum charge and furnace capacity, castings that take a full furnace.

Long downstream steps

Heat treatment, repairs, inspection and machining with their lead times.

Teams and shifts

Labour and machine time, moulding teams and shop working hours.

Delays explained

Orders at risk with the reason, before it is too late to warn the customer.

Request a demo → Discover the Fond/Wise foundry ERP

Worked example

A steel foundry has three large castings in its order book, all due in the same month, and two furnaces: furnace 1 of 4 tonnes and furnace 2 of 6 tonnes. Illustrative values.

Casting Poured weight Furnace Moulding and closing In-mould cooling
Pump body 5.5 t furnace 2, full charge 6 days 6 days
Cover 2.5 t furnace 1 3 days 3 days
Impeller 1.2 t furnace 1 4 days 3 days

The pump body needs the full charge of furnace 2, which cannot pour anything else that day. It occupies the large flask for almost two weeks between moulding and cooling. Cover and impeller together fit within the capacity of furnace 1: it pays to prepare them so that both moulds are ready for the same heat.

The sensible sequence is therefore: start the pump body first, as it is the longest, prepare cover and impeller in parallel for a joint heat on furnace 1, and check that the large flask is not needed for other orders before shakeout. If the cover pattern arrives from the patternmaker three days late, the whole plan has to be recalculated: that is when an alternative scenario, ready in minutes, makes the difference.

Frequently asked questions

What is the scarcest resource in hand moulding?

It depends on the foundry, but it is often floor space: every mould occupies an area for days or weeks, through moulding, curing, closing, pouring and cooling. Next come large flasks, cranes and teams of skilled moulders.

Why does in-mould cooling matter so much?

Because with large castings cooling can last days or weeks, and for all that time the flask and the floor space stay occupied. Pouring earlier or later changes the availability of flasks and space for every order that follows.

How do you schedule a casting that needs the full charge of a furnace?

By reserving the pouring day on that furnace, with the right alloy and temperature and the handling equipment available. The poured weight cannot exceed the capacity of the furnace and the ladle, and on that day the furnace cannot serve other heats: the plan has to take this into account.

How do you manage a pattern coming from the patternmaker or the customer?

By recording its status, location and expected arrival date, and linking it to the order. If the pattern is not available, the plan must know in advance and move the moulding, instead of finding out on the day.

Why is a scrapped casting more serious with large castings?

Because the value of a single casting is high and the time to remake it is long. A scrap found after cooling or at inspection pushes delivery back by weeks: that is why the plan must show the consequences and the alternatives straight away.