Production and planning

Die casting production scheduling: machines, dies, alloys and downstream steps

In high pressure die casting the cycle lasts a few seconds, but a die change can cost hours. Machines of different tonnage, dies due for maintenance after a given number of shots, holding furnaces with a single alloy, and trimming, machining and inspection downstream: scheduling decides how much the cells deliver.

RC Informatica technical team · Published November 21, 2026

Why die casting is a case apart

In high pressure die casting there is no moulding: the casting is formed in a metal die mounted on a machine, with cycles of a few seconds and large quantities. Capacity is very high but rigid: each machine can only work with certain dies, every die change costs hours and every die has a limited life. Scheduling decides how this capacity is used.

The challenges, one by one

Die and machine compatibility

Each die needs a minimum locking force and compatible dimensions. The largest machines are few and easily become the bottleneck, because some dies can only run there.

Die change

Removal, mounting, connections, preheating and adjustment take hours, and the first parts are often start-up scrap. The aim is to change as little as possible, but runs that are too long produce early and fill the warehouse.

Die life and maintenance

Dies have to be maintained after a given number of shots, and can go for repair because of wear or breakage. A die that is out of service blocks the item, often with no alternative.

Alloy per cell

Each cell usually has a holding furnace next to the machine, fed by a central melt shop. Changing alloy on a cell means emptying or replacing the furnace: in practice the alloy is a constraint of the cell.

Short cycles and continuous shifts

With cycles of a few tens of seconds and work often over several shifts, even short stoppages are worth many parts. The plan has to account for shifts, planned stoppages and the staff available for changes.

Downstream bottlenecks

After the machine come trimming and deburring, machining, impregnation, surface treatments, X-ray inspection or leak testing. The real limit on delivery is often here, not at the machine.

Customers and deliveries

Die casting works heavily for automotive customers, with frequent deliveries and schedules updated continuously. The plan has to be recalculated often without multiplying die changes.

How it is usually planned

The department manager assigns dies to machines in a spreadsheet, based on experience and urgencies. Die shot counts are noted separately, maintenance is done when the die starts to give problems, and the downstream steps follow their own programme.

The limits of spreadsheets and generic ERP systems

  • Dies not linked to the plan: a generic ERP does not know which dies run on which machines.
  • Die life ignored: maintenance is not planned and batches are interrupted.
  • Die changes not optimised: the cost of wrong sequences cannot be seen.
  • Downstream steps disconnected: the machine produces, but the finished part does not arrive on time.
  • No scenarios to assess a machine breakdown or a rush order.
Fond/Wise

How FOND/WISE handles it

FOND/WISE manages dies and tooling with their master data: items and impressions, status, location, photos, periodic maintenance set-up and maintenance log, with an alert when a die is under maintenance or unavailable. For each item there are alloy, weight, routings with internal and outside operations, labour and machine times and lead times, and progress comes in from the cells through the MES, including through the PLC connection.

FIP’s AI production scheduling calculates the machine plan with rules written in plain language, for example “die 120 only runs on machines of 1,600 t and above”, “at most one die change per shift per cell” or “the die goes for maintenance every 20,000 shots”. The plan covers several weeks, flags delays and bottlenecks, including downstream ones, and allows scenarios to be compared.

Discover AI scheduling on FIP →

Key features

Dies and maintenance

Die master data, periodic maintenance and unavailability alerts.

Die and machine compatibility

Rules on which machines each die can run on.

Die changes

Changes grouped and placed at the least costly moments.

Alloy per cell

Items assigned to the cells with the right alloy in the holding furnace.

Downstream steps

Trimming, machining, impregnation and inspection taken into account in the plan.

Data from the machines

Shots, scrap and downtime collected from the MES and the PLCs.

Request a demo → Discover the Fond/Wise foundry ERP

Worked example

An aluminium die casting department has three cells: two 1,600 t machines and one 2,500 t machine, all with holding furnaces in EN AC-46000. In the week it has to produce four items. Illustrative values.

Item Die Minimum machine Pieces Shots before maintenance
Gearbox housing S-01 2,500 t 4,000 5,000
Engine mount S-02 1,600 t 9,000 60,000
Cover S-03 1,600 t 6,000 40,000
Bracket S-04 1,600 t 3,000 2,500
  • The gearbox housing can only run on the 2,500 t machine, which becomes the critical resource of the week.
  • The bracket die reaches its maintenance threshold after 2,500 shots, before the 3,000 pieces are complete: the plan has to include the maintenance or split the batch in two.
  • Engine mount and cover can run on the 1,600 t machines: it pays to dedicate one cell to each for the whole week, avoiding die changes.
  • Downstream, machining of the engine mount has a capacity of 1,500 pieces a day: die casting 3,000 a day only fills the intermediate store.

Good scheduling does not maximise the shots of each machine, but the flow through to the finished, delivered part.

Frequently asked questions

Why is a die change so costly in die casting?

Because it requires removing and mounting the die, connections, preheating and adjustment, and the first parts are often start-up scrap. On machines with cycles of a few seconds, a change lasting a few hours is worth thousands of parts not produced.

How is die life taken into account in scheduling?

By recording the shots and the maintenance threshold of each die. The plan has to know when the die will go for maintenance, so as not to launch a batch it cannot complete, and to schedule maintenance at the least critical moments.

Can every die run on any machine?

No. The die needs a minimum locking force and dimensions compatible with the machine, as well as the right peripherals. Scheduling must assign each die only to compatible machines.

How are different alloys handled across the cells?

Each cell usually has a holding furnace with a single alloy. Changing alloy means emptying or replacing the furnace: it pays to assign alloys to cells on a stable basis and group items accordingly.

Why look at the downstream steps too?

Because trimming, machining, impregnation, treatments and X-ray inspection have their own capacity. If die casting produces more than the next step can process, only the intermediate store grows and deliveries do not improve.

Want to see Fond/Wise running on your foundry’s data?

Book a demo with the RC Informatica team — foundry software specialists since 1994.

Request a demo →