Why investment casting is scheduled differently
Lost wax investment casting produces precision castings, often in stainless steels, superalloys and special alloys, for sectors such as aerospace, medical, energy and precision engineering. The process is long and made up of many steps in sequence, some with fixed times that cannot be compressed. Scheduling does not just decide the order of work, but the real lead time and the amount of work in progress.
The challenges, one by one
Wax injection dies
Wax patterns are injected into dedicated dies, which are a resource to be planned just like patterns in a sand foundry: a die under maintenance blocks the item.
Tree assembly
Wax patterns are mounted on a sprue to form a tree. Different items of the same alloy can share a tree, if they are compatible in size and pouring conditions. Deciding what to put together affects yield, how well heats are filled and the delivery dates of several orders at once.
Ceramic shell and drying
The shell is built with several coats of ceramic slurry and refractory stucco, with minimum drying times between one coat and the next, under controlled temperature and humidity. The drying racks have a capacity: when they are full, new trees cannot go in.
Dewaxing and firing
The wax is removed in an autoclave or furnace, then the shell is fired before pouring. These are batch steps, with their own capacity.
Pouring by alloy
Pouring is done by alloy, often in vacuum furnaces or under controlled atmosphere for special alloys. The number of heats per day and the charge per heat are limited.
Lead time and work in progress
With many steps and fixed times, every order stays in process for weeks. Inserting a rush order moves all the others, and work in progress grows quickly if the plan is not balanced.
Scrap found late
Scrap shows up at pouring, at shell knockout or at inspection, that is weeks after launch. An increased quantity is launched based on historical scrap: a wrong calculation forces a second launch, with another full lead time.
Downstream steps and traceability
Cut-off, finishing, heat treatment, non-destructive and dimensional inspection, often with certifications required by the customer. Every part must stay linked to its tree and its heat.
How it is usually planned
The production manager follows the flow with a spreadsheet and experience of the slowest steps. Trees are assembled on the shop floor, drying is managed “by eye” on the racks, and delivery dates are promised by adding up average lead times.
The limits of spreadsheets and generic ERP systems
- Fixed times between steps ignored: the plan assumes times the process does not allow.
- Trees not managed: combining different items in the same heat is not planned.
- Drying capacity invisible: full racks are discovered on the shop floor.
- Over-launch quantities by guesswork: too many or too few parts compared with actual scrap.
- No scenarios to assess the effect of a rush order on all the others.
How FOND/WISE handles it
FOND/WISE manages production routings with the sequence of steps, internal and outside operations, labour and machine times and process lead times; dies with maintenance and unavailability alerts; the alloy and chemical analyses for each heat; and full traceability from the heat to the delivered casting. Progress on every step comes in from the shop floor through the MES, and MRP takes lead times and work in progress into account.
FIP’s AI production scheduling plans the steps with the shop’s rules written in plain language, for example “at least 6 hours between two shell coats”, “a tree only contains items of the same alloy” or “the vacuum furnace does at most 8 heats a day”. The plan covers several weeks, shows the load on every step and explains why an order is late.
Key features
Multi-step routings
Sequence of steps with times and process lead times.
Wax injection dies
Master data, maintenance and unavailability alerts.
Times between steps
Drying and waiting times between coats as plan rules.
Pouring by alloy
Trees and heats grouped by alloy.
Traceability by heat
From the delivered casting back to the heat, the analysis and the lot.
Progress by step
Quantities and scrap declared in the MES, step by step.
Worked example
A stainless steel investment foundry receives a rush order for 400 pieces of a small impeller, due in four weeks. The routing steps have these process times, without queues and waiting. Illustrative values.
| Step | Indicative time |
|---|---|
| Wax injection and tree assembly | 1–2 days |
| Ceramic shell: 7 coats with drying between coats | 4–5 days |
| Dewaxing and shell firing | 1 day |
| Pouring, shell knockout, cut-off | 1–2 days |
| Finishing, heat treatment, inspection | 3–5 days |
Process times alone add up to 10–15 working days. With queues between steps, the real lead time of a repeat order is often three weeks or more: the order can only be delivered if it starts at once. But the drying racks are already almost full: entering now, the order lengthens the lead times of the others.
With a historical scrap rate of 8% on the impeller, at least 435 pieces have to be launched. If each tree carries 24 pieces, 19 trees are needed, and the last one can be filled with other items of the same alloy.
Scheduling shows at once which orders slip if the impeller is inserted, and by how much, before the date is promised to the customer.
Frequently asked questions
Why does investment casting have such long lead times?
Because the process has many steps in sequence and some cannot be speeded up: the ceramic shell is built coat by coat, with fixed drying times between one coat and the next. On top of that come dewaxing, firing, pouring and finishing.
What is tree assembly?
Wax patterns are mounted on a sprue to form a tree, or cluster. Different items can share the same tree, provided they are of the same alloy and compatible in size and pouring conditions. Deciding what to put together affects yield, times and delivery dates.
Why is shell drying a bottleneck?
Because it needs rack space, controlled temperature and humidity, and minimum times between coats. When the racks are full, new trees cannot go in.
How is scrap handled in investment casting?
By launching an increased quantity based on the item’s historical scrap rate, because scrap shows up weeks later, at pouring or at inspection. The calculation has to be precise: too few means a second launch with another full lead time, too many creates surplus.
Is traceability more important in investment casting?
It is essential, because many customers operate in sectors such as aerospace, medical, energy and oil & gas, and because every tree and every heat must be linked to the parts, the analyses and the certificates.